Maintenance

During planned shutdown and modification periods the Terminal may require withdrawal of partial or full services.

TOTAL E&P UK makes every effort to reduce such periods and to liaise with National Grid Gas and field operators to co-ordinate timing of the shutdowns.

Standard maintenance periods are up to 45 days during a 3 year rolling period during the summer months, with a period for modifications of up to 20 days subject to 12 months notice.

Maintenance periods qualify for relief against "send or pay" and corresponding TOTAL E&P UK liability on failure to provide services.

Please note that we do not guarantee the accuracy of the information provided on this website and do not accept responsibility for any use you may make of the information. Although you are at liberty to download or print any information from this website, copyright remains with TOTAL E&P UK LTD at all times.