UK.Total Advert
Frigg UK Pipeline
print page

Entry Specification

A typical specification for gas delivered to the Frigg UK Terminal is set out below:

Cricondenbar and Cricondentherm are to be calculated (as required) based on the Peng-Robinson equation of state using the terminal operator’s current simulation package

Gas must be free from objectionable odours and from materials and dust or other solid or fluid mater, waxes, gums and gum-forming constituents.

No chemicals or other substances may be introduced into the gas which might be carried over into the Terminal facilities without the agreement of TOTAL E&P UK (such agreement not to be unreasonably withheld).

If a shipper delivers gas via the Frigg UK Pipeline, such shipper may be obliged to inject an agreed pipeline corrosion inhibitor at a rate specified by TOTAL E&P UK.

Although a Wobbe Index for the gas is not defined, it must be such that the Wobbe Index of sales gas exported to the Transco Terminal meets the required specification of 48.2 to 51.4 MJ/scm.

The Frigg UK Pipeline Entry Specification may be found here.

The gas will be redelivered to the Transco Terminal for entry into the National Transmission System (NTS) in a condition to meet the NTS Specification, with the CO2 content in accordance with the specification applicable to the Frigg UK Terminal (currently 4%).

Please note that we do not guarantee the accuracy of the information provided on this website and do not accept responsibility for any use you may make of the information. Although you are at liberty to download or print any information from this website, copyright remains with TOTAL E&P UK LTD at all times.