ullage profile

The ullage profile for the SIRGE System for each gas contract year is as follows:

  Capacity 2012 2013 2014 2015 2016
Pipeline 18.83 Msm3/d N/A N/A amber red red

Future modifications may increase capacity/ullage.

Ullage as % of system capacity  
<5% Red red
5% to 25% Amber amber
>25% Green green

The above ullage profile is for the SIRGE System Pipeline from the entry point at the Shetland Gas Plant to the exit point at the FUKA tie-in at MCP-01.  The ullage profile does not indicate ullage in any infrastructure upstream of the entry point or downstream of the exit point.  Pipeline capacity is nominally 665MMscfd (18.83MMscmd) and is owned on a divided rights basis.